Eindhoven Handling Cargo (EIN)

CLIENT
Eindhoven Airport (EIN)
Airport:
Eindhoven Airport (EIN)
Project place:
Eindhoven
Country:
The Netherlands
Start date:
2005, April
Commissioning date:
2006, January
Reference sheet
System description
ULD handling and storage system
Included components



  • 2 Truck docks 20 ft

  • 2 Truck docks 10 ft

  • 1 Transfer vehicle 20 ft with semi-automatic controls

  • 1 Lowering workstation 20 ft NEP with split operation (2x 10 ft) facility and double weighing system

  • 3 Lowering workstations 10 ft NEP with weighing system

  • 26 Motor powered roller decks

  • 2 Stand-alone floor scales (5.5 x 5.5 m 10 ton)

  • Slave pallet system

  • Delivery, installation, commissioning, training




Control System
Overall PLC control system